2006 - Hunter Road Services - John Hunter Hospital

This project involved the Boring of 600mm holes for 200mm steel post that would hold the precast panels.

Gongues installed a total 330 linear meters in 4 precast reinforced concrete retaining walls ranging from 1m to 3m high and 2 wire basket mass walls from 0.5 to 1m high.

The panels were precast by Gongues Constructions at Cameron Park, this site is now the home of the Gongues Constructions Head Office.

Precast panels being formed.

Panels just prior to pouring complete with renforcement and lifting lugs.

First batch of panels stripped.

One retaining wall ready for backfill.

The corner of one retaining wall at the second entrance to the John Hunter Hospital.